  • Project Panels Design & Factory Test “34 automation panels”.
  • Application Design and Programming (4 PLCs s7-300) with (16 RIO units).
  • Network configuration (fiber optic converter - switches – Profinet - Profibus )
  • Pressure, Level and Flow PID Programming and commissioning.
  • Configuring and optimizing SCADA WinCC 7.4.
  • Plant’s Daily Reports programming using visual scripts.
  • ِhistorian servers.